A casting incoming inspection plan is the document that decides, before the first pallet arrives, which characteristics get measured, how many pieces get pulled, and what happens when a reading lands exactly on the limit. Buyers who skip it rarely save inspection money. They move the argument to the morning a machining line stops and nobody can prove whether the bore or the fixture was wrong.
This guide works through the four decisions a casting incoming inspection plan has to make, using a real shape of order: 1,200 ductile iron pump housings per lot, 12 lots a year, a Ø40 mm seal bore held to +0.050/0.000 mm, and an as-cast surface judged against ASTM A802 visual comparators. The sampling arithmetic follows ISO 2859-1, the measurement decision rules follow ISO 14253-1, and the gauge numbers come from our own shop-floor MSA studies. Where the maths says the conventional answer is wrong, it says so.

What a Casting Incoming Inspection Plan Decides Before Any Part Is Measured
Three things, and only three: what matters, how many samples, and who has the authority to say no. Everything else in the document is paperwork around those three decisions. A plan that runs to forty pages but leaves the sample size per characteristic unstated is not a plan; it is a wish list with a signature.
It also has a different job from the two documents buyers usually confuse it with. The casting quality agreement fixes the contractual acceptance standards and the liability split. The contrôle du premier article proves the process once, at the start. The incoming plan is the recurring instrument: it runs on every lot, in your own receiving area, with your own gauges, and it produces the record you will need if a lot has to go back. If the quality agreement is the law and FAI is the commissioning test, the incoming plan is the police patrol.
The user of the document is not the quality manager. It is a receiving inspector with 40 minutes, a cart of parts and a gauge that may or may not be in calibration. Every line has to be executable by that person without a phone call.
The Four Columns Every Inspection Line Needs
One row per characteristic, four columns: what it is, how bad a miss would be, what standard defines acceptance, and how many pieces get checked. That is the entire skeleton of a workable casting incoming inspection plan, and every argument about inspection cost traces back to one of those four cells. When a row cannot be filled in, the characteristic probably should not be on the plan at all.
| Class | Typical casting characteristics | Acceptance basis | Sample and gauge |
|---|---|---|---|
| Critical | Pressure boundary wall, seal bore, thread engagement below 1.5D, lifting point section | AQL 0.65, or 100% plus pressure test; radiography per ASTM E446 where specified | 100% or n = 80; CMM, air gauge, hydro test |
| Major | Machined face flatness, bolt pattern position, non-sealing bore, wall thickness at a defined section | AQL 1.0 to 2.5 per ISO 2859-1, drawing tolerance per ISO 8062-3 for as-cast dims | Code letter per lot size; plug gauge, height gauge, ultrasonic thickness |
| Minor | As-cast surface, coating thickness, flash, marking legibility, core print witness | AQL 4.0; ASTM A802 visual comparators for surface, not a dimensional callout | Code letter; comparator plates, coating gauge, visual |
The classification test is not technical, it is financial: if the failure mode is discovered by the end user rather than by the next operation, the characteristic is critical regardless of how small the tolerance is. A 0.3 mm step on a cosmetic cover is minor. A 0.3 mm shortfall in thread engagement on a 12 bar housing is not, even though both are dimensional.
The most common structural error in a casting incoming inspection plan is a single sampling line for the whole drawing. A 26-characteristic plan that applies one AQL 2.5, n = 80 line to everything gives 26 separate chances for a lot whose worst characteristic sits at 5% defective to walk through the door. Sampling plans do not average across characteristics; each row carries its own risk.
Sampling Rules That Make a Casting Incoming Inspection Plan Defensible
ISO 2859-1 is mechanical once you accept its logic: lot size gives a code letter in the casting incoming inspection plan, the code letter gives a sample size, and the AQL gives an acceptance number. Nothing about it is intuitive, which is exactly why it survives audits — the numbers are traceable to a table rather than to a judgement call made on a Tuesday.
| Code letter | Lot size | n | AQL 0.65 | AQL 1.0 | AQL 2.5 | AQL 4.0 |
|---|---|---|---|---|---|---|
| F | 91 – 150 | 20 | 0 / 1 | 0 / 1 | 1 / 2 | 2 / 3 |
| H | 281 – 500 | 50 | 1 / 2 | 1 / 2 | 3 / 4 | 5 / 6 |
| J | 501 – 1,200 | 80 | 1 / 2 | 2 / 3 | 5 / 6 | 7 / 8 |
| K | 1,201 – 3,200 | 125 | 2 / 3 | 3 / 4 | 7 / 8 | 10 / 11 |
| L | 3,201 – 10,000 | 200 | 3 / 4 | 5 / 6 | 10 / 11 | 14 / 15 |
For the 1,200-piece housing lot the code letter is J, the sample is 80 pieces, and an AQL 2.5 line means accepting the lot at 5 defectives and rejecting at 6. That is the whole rule. Notice what it does not say: it does not say the lot contains 2.5% defects, and it does not say 5 defects is acceptable engineering. It says a lot at the AQL quality level will be rejected 5% of the time — the producer’s risk — and a lot substantially worse than the AQL has a defined, calculable chance of being caught.
Two habits make the table survive an audit. First, tie each row to a drawing revision, because a plan written against Rev C of a drawing is worthless once Rev D moves the datum. Second, record the actual Ac/Re pair, not just the AQL — auditors and suppliers both misread a bare “AQL 2.5” line, and the pair removes the argument. Our inspection method selection guide covers which of VT, PT, MT, UT and RT fits each characteristic; the sampling plan then decides how often each is applied.
Why AQL 2.5 Is Not a Quality Level
The acceptance probability of the plan is what the buyer actually experiences, and it is not obvious from the AQL number. Running the binomial for the three plans above:
| Incoming defect rate | J, n=80, Ac 5 (AQL 2.5) | K, n=125, Ac 7 (AQL 2.5) | J, n=80, Ac 2 (AQL 1.0) |
|---|---|---|---|
| 0.5% | 100.0% | 100.0% | 99.2% |
| 1.5% | 99.9% | 99.9% | 88.1% |
| 2.5% | 98.5% | 98.6% | 67.7% |
| 4.0% | 89.9% | 87.1% | 37.5% |
| 5.0% | 78.9% | 71.2% | 23.1% |
| 6.5% | 58.0% | 43.0% | 10.1% |
| 10.0% | 17.7% | 6.0% | 1.1% |
Read the 2.5% row: a supplier running exactly at the AQL ships 2.5% defective parts, and the plan accepts 98.5% of those lots. The average outgoing quality of this rectifying scheme works out to about 2.30% — of the 1,120 pieces that pass, roughly 26 are defective. At a $46 cost per escape, that is about $1,184 per lot against $59 of inspection. The plan looks cheap only because the supplier in the example is actually running near 0.5%, where the acceptance probability is 100% anyway.
That asymmetry is the single most useful thing to understand about a casting incoming inspection plan: it is a filter calibrated to the supplier’s current process, not a screen that guarantees quality. Tightening from AQL 2.5 to AQL 1.0 on the same sample size drops acceptance at 2.5% defective from 98.5% to 67.7% — you buy 31 percentage points of detection for the same 80 pieces of handling. On a seal bore we normally go further: 100% air gauge, because the escape cost of one leaking housing at the customer is larger than the entire annual inspection budget.
Gauge Capability Inside a Casting Incoming Inspection Plan
The gauge half of a casting incoming inspection plan is where most plans quietly fail: a sampling plan is only as good as the instrument behind it. The working rule is 10:1 — gauge resolution should be one tenth of the tolerance, so a 0.050 mm bore tolerance needs 0.005 mm of resolution before repeatability is even discussed. Anything coarser turns the accept/reject decision into a coin toss dressed in numbers.
| Instrument | Resolution | GRR (mm) | % of 0.050 tolerance | Verdict |
|---|---|---|---|---|
| Dial bore gauge | 0.001 mm | 0.0120 | 24.1% | Conditional — trend only, not a lot decision |
| Air gauge | 0.0005 mm | 0.0045 | 9.1% | Accept for 100% screening of the bore |
| CMM (MPE 2.7 µm) | 0.0001 mm | 0.0036 | 7.2% | Accept — referee gauge and FAI |
| Vernier caliper | 0.02 mm | 0.0300 | 60.0% | Reject — unusable for this feature |
The GRR figure is the square root of repeatability squared plus reproducibility squared, taken from a 3-operator, 10-part study; the uncertainty budget behind it follows the measurement practice described by NIST metrology guidance. Under the usual reading, below 10% is acceptable, 10 to 30% is conditional and needs a stated reason, and above 30% the gauge cannot support a conformance decision. The dial bore gauge at 24.1% is the classic receiving-area trap: it is accurate enough to show a trend across lots and not accurate enough to reject a single piece at the limit.
Tolerance class also decides which gauges are worth buying. On the same drawing the as-cast wall may carry a tolerance 20 to 40 times looser than the machined bore, so it gets a comparator plate and a caliper, while the bore gets air gauge and CMM. Trying to apply one instrument family across both ends of that spread is how receiving areas end up with 40 calibrations a year and no defensible records. Dimensional tolerance practice for as-cast features is set out in ISO 8062-3, and surface acceptance for as-cast faces belongs in the casting tolerance framework rather than in a note on the inspection sheet.
Guard Bands: Deciding at the Limit
ISO 14253-1 exists because a measured value of 40.049 mm inside a 40.000 to 40.050 mm tolerance is not proof of conformity. With an expanded uncertainty of 0.003 mm, that reading is compatible with a true value of 40.052 mm, which is scrap. The standard’s answer is a guard band: shrink the acceptance zone by the uncertainty on each side, so the zone becomes 0.044 mm wide and the 3 µm at each end is treated as indeterminate.
Twelve percent of the tolerance band then becomes a decision rather than a measurement, which is the part of a casting incoming inspection plan that buyers argue about most. Buyers usually hate guard bands because they reject parts the supplier’s gauge passes. The honest framing is that the parts were always ambiguous; the guard band only makes the ambiguity visible and puts a rule around it. For a seal bore we reject in the guard band and rework, because a re-machined bore costs $8 while a leak at the customer costs four figures. For a cosmetic face we accept in the guard band, because the consequence is a repaint.
This is also where the argument with a supplier usually starts, and the fix is procedural rather than technical: name the referee gauge in the plan, state its uncertainty, and state that disputed readings go to a third party under ISO/IEC 17025 accreditation. Written before the dispute, that clause ends most disputes in one email.

What a Casting Incoming Inspection Plan Costs Per Lot
The 100%-versus-sampling question that every casting incoming inspection plan has to answer is settled by arithmetic faster than by procedure. Take the 1,200-piece lot, a receiving inspector loaded at $38/hour, 52 seconds per piece for visual plus dimensional plus thread check, and 0.4 hours of setup per lot. Sample of 80 costs $59.11 per lot; inspecting all 1,200 costs $673.87. At a $46 cost per escaped defective — replacement casting, line rework, admin — the premium of $614.76 buys 13.4 prevented escapes, which only happens once the incoming defect rate passes 5.07%.
| Strategy at 1.5% incoming defects | Inspection per year | Escapes per year | Escape cost | Total |
|---|---|---|---|---|
| Certificate plus annual supplier audit only | $0 | 216 | $9,936 | $9,936 |
| AQL 2.5 sampling, n = 80 per lot | $709 | 0.3 | $13 | $722 |
| Sampling plus 100% air gauge on the seal bore | $2,533 | 0.3 | $13 | $2,546 |
| 100% visual and dimensional, all features | $8,086 | 0 | $0 | $8,086 |
The cost table above makes two points that procurement teams tend to resist when a casting incoming inspection plan is first drafted. First, sampling is not a compromise between cost and quality — at a healthy supplier it is 13 times cheaper than doing nothing and 11 times cheaper than inspecting everything, with the same escape rate. Second, 100% inspection becomes rational precisely when the supplier is bad enough to replace. Spending $8,086 a year to sort a process that should be fixed is the most expensive way to avoid a difficult conversation.
Where 100% does pay is narrow and targeted: the two or three characteristics whose escape cost is an order of magnitude above the rest. On a pressure housing that is the seal bore and the pressure test. On an fonderie à cire perdue it is usually a wall section or an internal passage that cannot be gauged after the fact, and on moulage sous haute pression the cavity fill itself is the characteristic that decides scrap. The plan should name those, and nothing else.
What to Do When a Lot Fails
A rejection is a process, not a decision. Four steps, all of them written into the plan in advance, keep a failed lot from becoming a failed relationship:
- Quarantine with the sample intact. Keep the 80 pieces and their readings, not just the 6 defectives. If the supplier disputes the call, the retained sample is the only evidence that cannot be re-measured into agreement.
- Re-measure with the referee gauge. A second reading on the same dial bore gauge changes nothing. A CMM re-check of the 6 pieces costs about $90 and either confirms the rejection or exposes a gauge problem on your own side.
- Choose a disposition, not a mood. Return to vendor, 100% sort at the supplier’s cost, use-as-is with a written concession and a price adjustment, or rework in-house and debit. Use-as-is without a concession signature is how defective parts become installed parts.
- Open a corrective action with a date. Eight-discipline or five-why, root cause, containment, verification lot. The defect claim process covers the evidence package and the cost stack; the inspection plan only has to trigger it.
Skip the second step and you will eventually reject a good lot on a bad gauge. That error is more expensive than a missed defect, because it teaches everyone to distrust the inspection data.
Ten Lines That Make the Casting Incoming Inspection Plan Auditable
The document itself is one page per part number, controlled like a drawing, and a casting incoming inspection plan that runs longer than that is usually two plans stapled together. Ten fields, in this order, are enough for an auditor and enough for the receiving bench:
- Part number and drawing revision, with the revision letter in the header. A plan without a revision is an undated photograph.
- Characteristic list with class, one row each, numbered to match the drawing balloon numbers.
- Acceptance standard per characteristic, by clause — ASTM A802 for visual, ASTM E446 severity for radiography, ISO 8062-3 for as-cast dimensions, drawing tolerance for machined features.
- Sample size, frequency and Ac/Re, per row, with the ISO 2859-1 code letter stated rather than implied.
- Gauge identification and calibration due date, by asset number. “Bore gauge” is not a gauge, it is a category.
- MSA status, with the GRR percentage on file. A gauge that has never been studied has an unknown capability, not a good one.
- Record format and retention period, tied to the quality agreement — three years is common, seven or longer for pressure and safety parts.
- Disposition authority, by name or role, including who may sign a use-as-is concession. Never “quality department”.
- Traceability link, heat number or lot code recorded at receipt so a failed characteristic can be traced back to a melt and forward to finished goods.
- Revision history and approval, two signatures, date, and the reason for each change.
Two failure modes account for most of the audit findings we see. The first is an uncontrolled plan: the drawing moves from Rev C to Rev D, the plan does not, and inspectors spend a quarter checking a datum that no longer exists. The second is an unrecorded plan: readings live in a notebook or a spreadsheet on one laptop, which means the lot is technically uninspected the moment that person leaves. Both are cheap to prevent and expensive to discover.
For buyers running several casting processes at once — including parts that leave the foundry for CNC machining — the same ten lines work across moulage au sable, moulage sous pression et pattern and tooling suppliers; what changes is the characteristic list and the acceptance clause, not the structure. On iron castings the pressure test simply becomes the first row instead of the last. Teams that already audit their supply base can fold this into the supplier audit scorecard as a document-review item worth points, which is often the fastest way to get a plant to write one.

FAQ
How many pieces should we inspect from a 1,200-piece casting lot?
Inside a casting incoming inspection plan, a lot of 501 to 1,200 pieces under ISO 2859-1 gives code letter J and a sample of 80. At AQL 2.5 that is accept 5, reject 6. If a characteristic is critical — a seal bore, a pressure wall — the sample size is irrelevant and 100% inspection applies, because the plan is not designed to detect a single defective piece with certainty.
Can the supplier’s inspection certificate replace our incoming inspection?
No, but it can reduce it. A certificate describes the supplier’s sample and its measurement system, not your lot, so it can justify a lighter casting incoming inspection plan but never an absent one. The usual compromise is reduced inspection after a documented run of accepted lots — commonly ten consecutive lots with no rejection and no change of process — which halves the sample while keeping the record trail intact. Drop the incoming check entirely and you own the escape cost with no evidence.
What AQL should we use for cosmetic defects on as-cast surfaces?
AQL 4.0 is the common starting point for minor cosmetic characteristics, judged against ASTM A802 comparator plates rather than a written description of roughness. Keep cosmetics on a separate row from functional characteristics: mixing “light surface porosity” into a dimensional line is how a supplier ends up rejecting serviceable parts and shipping a leaking one in the same lot.
How long should inspection records be kept?
Three years is the common contract figure for commercial castings; pressure-retaining and safety-related parts usually require seven years or the service life of the assembly, whichever is longer. Whatever the number, put it in the quality agreement and mirror it in the plan, because “we keep them somewhere” fails the first serious audit.
Does an incoming inspection plan replace first article inspection?
No. FAI validates that the process can make the part to print, once, before volume; the incoming plan monitors every lot afterwards. A part that passed FAI on 3 samples and drifts 0.02 mm two months later will pass an FAI record review and fail a lot. The two documents answer different questions. A complete supplier file carries both: the casting incoming inspection plan produces a new record every month, the FAI record proves the process once, and the tolerance stack analysis that explains why the limits were set where they were.
If your casting incoming inspection plan is still being written, start from the Guide sur la fonderie des métaux for the process background, then take the characteristic list from the drawing and the acceptance clauses from the quality agreement. The défauts courants de moulage catalogue is a useful cross-check for which rows actually earn their place — a characteristic that no process variation can move does not need a sample size.
À la recherche d'une fonderie de métaux fiable en Chine ?
- Nous pouvons vous aider à optimiser la conception de vos produits et à réduire vos coûts.
- Nous pouvons vous aider avec des pièces moulées de haute qualité et en grande quantité.
- Nous pouvons livrer à temps et obtenir de nouvelles opportunités de marché.
- Vous bénéficierez du service de moulage de métaux proposé par Supro MFG.
*Sampling probabilities computed with the binomial distribution for the stated n and Ac; costs based on Supro MFG receiving-area time studies. Standards referenced: ISO 2859-1, ISO 14253-1, ISO 8062-3, ASTM A802, ASTM E446.